delivery-timeline

Generates a delivery timeline from a completed milestones.yaml. Asks for a production deploy date, QA rounds, and days per QA session. Updates each milestone with estimated_days, produces timeline.yaml with a complete relative-day schedule, and appends a workback block mapping every item to a real calendar date working backwards from the production deploy date.

How do I install this agent skill?

npx skills add https://github.com/validkeys/sherpy --skill delivery-timeline
view source ↗

Is this agent skill safe to install?

  • Gen Agent Trust Hubpass

    The delivery-timeline skill is a legitimate utility designed for project management. It calculates project schedules by reading local milestone files, processing user-provided dates, and generating output files. No malicious patterns, network exfiltration, or unauthorized privilege escalations were detected.

  • Socketpass

    No alerts

  • Snykpass

    Risk: LOW · No issues

What does this agent skill do?

Delivery Timeline

Generates a delivery timeline from a completed milestones.yaml. Asks for delivery parameters (production deploy date, QA rounds, days per QA session), updates milestones with day estimates, and produces timeline.yaml with two sections: a relative-day timeline and a real-date workback schedule anchored to the production deploy date.

Prerequisites

  • Completed {base_directory}/implementation/milestones.yaml (output from /implementation-planner)

Usage

/delivery-timeline [base-directory]

If no directory is provided, auto-detect by looking for implementation/milestones.yaml in the current directory.

If not found, prompt the user: "Where are your planning artifacts located?"

Wait for the user to provide a path before proceeding. Store as base_directory.

Process

Step 1: Determine Base Directory and Load Milestones

If no directory parameter was provided, check if implementation/milestones.yaml exists in the current directory.

  • If found, use current directory as base_directory
  • If not found, prompt: "Where are your planning artifacts located?" and wait for user response

Once base_directory is determined:

Read {base_directory}/implementation/milestones.yaml and extract each milestone's id, name, dependencies, and estimated_duration.

Also read meta.ordering_strategy if present. Store as ordering_strategy. If absent, default to foundation-first.

The ordering_strategy value drives structural differences in Steps 6 and 7:

  • multi-pr: PR/review/merge cycles are inserted after each milestone in the development timeline; the fixed pre-QA PR block in Step 7 is omitted.
  • All other strategies (single-feature-branch, value-first, risk-first, vertical-slice, foundation-first): standard single-PR post-development flow (no change to current behavior).

Step 2: Gather Delivery Parameters

Ask the user the following three questions. You may present them together in a single message:

  1. Production deploy date — "What is your desired production deploy date? (YYYY-MM-DD)"
  2. QA rounds — "How many rounds of QA are required?"
  3. QA days per round — "How many days should be allotted for each QA session?"

If the provided production deploy date falls on a Saturday or Sunday, warn the user:

"Note: [date] falls on a weekend. Would you like to use [previous Friday] or [next Monday] instead?"

Wait for the user to confirm or correct before proceeding. Store the confirmed values as:

  • production_deploy_date (ISO 8601 date string)
  • qa_rounds (integer ≥ 1)
  • qa_days_per_round (integer ≥ 1)

Step 3: Convert Durations to Days

Convert each milestone's estimated_duration string to a whole number of business days using this table:

estimated_durationestimated_days
0.5 weeks3
1 week5
1.5 weeks8
2 weeks10
2.5 weeks13
3 weeks15
3.5 weeks18
4 weeks20
N weeksN × 5 (rounded up to nearest whole day)

For durations expressed in days already (e.g., 5 days), use the number as-is.

Step 4: Update milestones.yaml

Add estimated_days to every milestone entry in {base_directory}/implementation/milestones.yaml. Do not modify any other fields.

Example — before:

- id: m0
  name: Foundation & Project Setup
  estimated_duration: 1 week

After:

- id: m0
  name: Foundation & Project Setup
  estimated_duration: 1 week
  estimated_days: 5

Step 5: Determine Project Size

Calculate total_development_days by summing estimated_days across all milestones.

Large project if either condition is true:

  • total_development_days > 30
  • Number of milestones > 5

Large projects receive two rounds of QA feedback by default, but this is overridden by the user-provided qa_rounds value from Step 2. is_large_project is still recorded in the summary for informational purposes.

Step 6: Build the Development Timeline

Starting at Day 0, assign a completion_day to each milestone in dependency order. Each milestone's start_day is the business day after its last dependency completes (or 0 if no dependencies). Its completion_day is start_day + estimated_days.

Day calculation formula:

  • No dependencies: start_day = 0
  • Has dependencies: start_day = max(dependency.completion_day) + 1 (next business day after dependencies complete)
  • completion_day = start_day + estimated_days

For sequential milestone chains (each depends on the previous):

m0: start_day=0, completion_day=0+estimated_days(m0)=5
m1: start_day=5+1=6, completion_day=6+estimated_days(m1)=16
m2: start_day=16+1=17, completion_day=17+estimated_days(m2)=27
...

For parallel milestones (sharing same dependency), they all start the day after that dependency completes. They share the same start_day but their completion_day is calculated independently based on their individual estimated_days.

Standard strategies (all except multi-pr)

last_milestone_day = the highest completion_day among all milestones.

multi-pr strategy

After each milestone, insert four PR cycle phases before the next milestone may start. Use the milestone id as a prefix (e.g. for m0: m0-pr-creation, m0-pr-review, m0-review-feedback, m0-merge).

id patternname patternestimated_daysnotes
[milestone-id]-pr-creation[Milestone Name] PR Creation0Opened on milestone completion_day
[milestone-id]-pr-review[Milestone Name] PR Review2
[milestone-id]-review-feedback[Milestone Name] Review Feedback Implementation2
[milestone-id]-merge[Milestone Name] Merge0Same day as review-feedback completion

The PR cycle adds 4 business days of overhead after each milestone. The next milestone's start_day = completion_day of its predecessor's merge phase + 1 (starts the day after merge completes).

For sequential milestones under multi-pr:

m0: start_day=0, completion_day=0+estimated_days(m0)=5
m0-pr-creation: start_day=5, completion_day=5          # 0 days, opens same day
m0-pr-review: start_day=5, completion_day=5+2=7
m0-review-feedback: start_day=7, completion_day=7+2=9
m0-merge: start_day=9, completion_day=9                # 0 days, merges same day

m1: start_day=9+1=10, completion_day=10+estimated_days(m1)=20
# ... repeat for each milestone

For parallel milestones under multi-pr, each branch gets its own PR cycle. A milestone depending on multiple parallel predecessors starts the day after the latest merge completion_day among them (max(merge.completion_day) + 1).

last_milestone_day = the highest completion_day of the final [milestone-id]-merge phase across all milestones.

Step 7: Append Post-Development Timeline

Add delivery phase items starting from last_milestone_day. Each item has a start_day (day the work begins) and completion_day (day the work is done). Items with estimated_days: 0 complete on the same day they start.

Use qa_rounds and qa_days_per_round from Step 2 to drive the QA section.

Fixed Pre-QA Phases

Standard strategies (all except multi-pr): Include the full PR/merge/deployment block below. This represents the single end-of-project PR.

idnameestimated_daysnotes
post-pr-creationPR Creation0Opened on last milestone day
post-pr-reviewPR Review2
post-review-feedbackReview Feedback Implementation2
post-mergeMerge0Same day as feedback impl
post-deploymentDeployment1

multi-pr strategy: Omit post-pr-creation, post-pr-review, post-review-feedback, and post-merge — those cycles already occurred per-milestone in Step 6. Start directly with post-deployment.

idnameestimated_daysnotes
post-deploymentDeployment1Final deployment after all milestones merged

QA Phases (repeated for each round 1..qa_rounds)

For each round R from 1 to qa_rounds, generate the following phases using qa_days_per_round as the QA Deadline duration. Use round-specific ids (e.g. post-qa-r1-deadline, post-qa-r2-deadline). When qa_rounds == 1, ids may omit the round suffix (e.g. post-qa-deadline).

id patternname patternestimated_daysnotes
post-qa-rR-deadlineQA Deadline (Round R)qa_days_per_roundTime allotted for QA team testing
post-qa-rR-feedback-implQA Feedback Implementation (Round R)3 if (R == 1 and qa_rounds > 1) else 2
post-qa-rR-prQA PR (Round R)0
post-qa-rR-feedbackQA Feedback (Round R)2 if (R == 1 and qa_rounds > 1) else 1
post-qa-rR-mergeQA Merge (Round R)0

Fixed Post-QA Phase (all projects)

idnameestimated_days
post-signoffSignoff1

Step 8: Build Workback Schedule

Map every timeline item (milestones + delivery phases) to a real calendar date by working backwards from production_deploy_date.

Anchor point: production_deploy_date = the real date for completion_day of post-signoff (the final day of the timeline, total_delivery_days).

Business day arithmetic: When counting backwards, skip Saturdays and Sundays. One business day back from a Monday is the previous Friday.

For each timeline item:

  • completion_date = production_deploy_date minus (total_delivery_days − item.completion_day) business days
  • start_date = production_deploy_date minus (total_delivery_days − item.start_day) business days

project_start_date = production_deploy_date minus total_delivery_days business days (Day 0).

Include all items from timeline in the same order. Also append a final entry for production-deploy with date: production_deploy_date.

Step 9: Generate timeline.yaml

Write {base_directory}/delivery/timeline.yaml.

Create directory if it doesn't exist:

mkdir -p {base_directory}/delivery

Output Format

Updated milestones.yaml

The estimated_days field is added to each milestone entry. All other content is preserved exactly.

timeline.yaml Schema

The output document includes: version, project, generated, milestones_file, summary (total days, project size, QA rounds, delivery model), timeline (milestones + delivery phases with start_day/completion_day/estimated_days), and workback (production deploy date, project start date, real calendar schedule).

See references/output-spec.md for the complete document specification with all fields, phase types, and workback calculation rules.

See references/example.yaml for a full example.

Example Output

See references/example.yaml for a complete sample timeline.

Gap Analysis

After generating timeline.yaml, perform a gap analysis and report findings inline.

Checks

Coverage

  • Every milestone in milestones.yaml appears in timeline.yaml
  • All milestone dependencies are respected (no milestone completes before its dependencies)
  • estimated_days was added to every milestone in milestones.yaml

Duration Reasonableness

  • No single milestone has estimated_days: 0 (flag for review)
  • No milestone exceeds 30 days without a note explaining the scope
  • Duration conversions match the table in Step 2

Project Size Classification

  • is_large_project correctly reflects total_development_days > 30 OR milestone_count > 5
  • QA rounds in timeline.yaml match user-provided qa_rounds
  • QA Deadline phases each use qa_days_per_round days

Delivery Model

  • ordering_strategy was read from milestones.yaml (or defaulted to foundation-first)
  • delivery_model in timeline.yaml summary matches the resolved strategy
  • For multi-pr: each milestone has a corresponding [milestone-id]-pr-creation / pr-review / review-feedback / merge block in the timeline; post-pr-creation through post-merge are absent from post-development phases
  • For all other strategies: post-pr-creation through post-merge are present in post-development phases; no per-milestone PR blocks exist

Timeline Integrity

  • completion_day values are strictly increasing for sequential milestones
  • Parallel milestones have correct independent completion_day values
  • Post-development phases follow immediately after last_milestone_day
  • total_delivery_days = completion_day of post-signoff

Workback Integrity

  • project_start_date = production_deploy_date minus total_delivery_days business days
  • production-deploy entry date matches production_deploy_date
  • All completion_date values are on weekdays (Mon–Fri)
  • workback.schedule contains all entries from timeline in the same order
  • post-signoff completion_date = production_deploy_date

Gap Analysis Report

After generating files, output a brief inline report:

## Timeline Gap Analysis

**Project:** [name]
**Delivery Model:** [ordering_strategy]
**Total Development Days:** [n] ([n] weeks)
**Total Delivery Days:** [n] (including post-dev phases)
**Project Size:** [Small / Large] ([reason if large])
**QA Rounds:** [n] × [qa_days_per_round] days each
**Production Deploy:** [YYYY-MM-DD]
**Project Start:** [YYYY-MM-DD]

**Checks:**
✓ All [n] milestones included
✓ Dependency order respected
✓ Duration conversions applied
[✓ / ✗] estimated_days added to milestones.yaml
[✓ / ✗] QA rounds match user-specified value ([n] rounds)
[✓ / ✗] All workback dates land on weekdays
[✓ / ✗] post-signoff completion_date = production_deploy_date

**Issues:** [none / list issues]

**Recommendations:** [none / list recommendations]

If issues are found, ask:

"I found the following timeline issues:

  • [Issue 1]
  • [Issue 2]

Would you like to:

  1. Fix these issues now
  2. Proceed with the timeline as-is
  3. Manually adjust the estimates before generating"

Add the canonical catalog link to the repository README so users can inspect current installs and available audits. The publishing guide covers the complete discovery path.

<a href="https://skillzs.dev/skills/validkeys/sherpy/delivery-timeline">View delivery-timeline on skillZs</a>