project-schedule-template
Эксперт по расписаниям проектов. Используй для WBS, Gantt charts, dependency mapping и resource allocation.
How do I install this agent skill?
npx skills add https://github.com/dengineproblem/agents-monorepo --skill project-schedule-templateIs this agent skill safe to install?
- Gen Agent Trust Hubpass
The skill consists entirely of project management documentation and templates with no executable code or security risks identified.
- Socketpass
No alerts
- Snykpass
Risk: LOW · No issues
- Runlayerwarn
1/1 file flagged
What does this agent skill do?
Project Schedule Template Expert
Expert in project scheduling, WBS, timeline management, and resource allocation.
Work Breakdown Structure (WBS)
wbs_principles:
100_percent_rule: "WBS must include 100% of project scope"
mutual_exclusivity: "No overlapping work between elements"
appropriate_detail: "Break down until estimable (8-80 hours)"
numbering:
level_1: "1.0, 2.0 (Phases)"
level_2: "1.1, 1.2 (Deliverables)"
level_3: "1.1.1 (Work packages)"
wbs_template:
- id: "1.0"
name: "Initiation"
deliverables:
- "1.1 Project Charter"
- "1.2 Stakeholder Analysis"
- id: "2.0"
name: "Planning"
deliverables:
- "2.1 Project Plan"
- "2.2 Technical Design"
- id: "3.0"
name: "Execution"
deliverables:
- "3.1 Development"
- "3.2 Testing"
- id: "4.0"
name: "Deployment"
deliverables:
- "4.1 Production Release"
- id: "5.0"
name: "Closure"
deliverables:
- "5.1 Documentation"
- "5.2 Lessons Learned"
Dependencies
dependency_types:
finish_to_start:
code: "FS"
description: "Successor starts when predecessor finishes"
most_common: true
start_to_start:
code: "SS"
description: "Both start together"
finish_to_finish:
code: "FF"
description: "Both finish together"
lag_lead:
lag: "FS+5 = Start 5 days after"
lead: "FS-3 = Start 3 days before finish"
Duration Estimation
three_point_estimation:
formula: "(O + 4M + P) / 6"
definitions:
optimistic: "Best case (10% probability)"
most_likely: "Most probable duration"
pessimistic: "Worst case (10% probability)"
example:
optimistic: 10
most_likely: 15
pessimistic: 26
result: "16 days"
risk_buffers:
low_risk: "10-15%"
medium_risk: "20-30%"
high_risk: "40-50%"
Resource Allocation
resource_planning:
max_utilization: "80% recommended"
buffer: "20% for meetings, admin, unexpected"
capacity_formula: "Working Days × Hours/Day × Availability %"
resource_leveling:
techniques:
- "Delay non-critical tasks"
- "Split tasks"
- "Add resources"
- "Overtime (short-term only)"
Critical Path
critical_path:
definition: "Longest path determining minimum duration"
characteristics:
- "Zero total float"
- "Delay impacts project end date"
calculations:
early_start: "Max(predecessor early finishes)"
early_finish: "Early start + Duration"
late_finish: "Min(successor late starts)"
late_start: "Late finish - Duration"
total_float: "Late start - Early start"
Phase Guidelines
phase_duration:
initiation: "5-10%"
planning: "15-25%"
execution: "50-70%"
closure: "5-10%"
Лучшие практики
- WBS first — начинайте с полной декомпозиции работ
- Realistic estimates — используйте трёхточечную оценку
- Buffer planning — закладывайте буферы на риски
- Critical path focus — приоритизируйте критический путь
- Resource leveling — избегайте перегрузки
- Regular updates — обновляйте расписание еженедельно
How can the creator link this skill?
Add the canonical catalog link to the repository README so users can inspect current installs and available audits. The publishing guide covers the complete discovery path.
<a href="https://skillzs.dev/skills/dengineproblem/agents-monorepo/project-schedule-template">View project-schedule-template on skillZs</a>